Performance specified work in construction contracts
The phrase ‘performance specified work’ refers to aspects of a building development that are identified in contract documentation to be designed by contractors or suppliers.
Specifications vary considerably depending on the stage to which the design has been developed, ranging from performance (open) specifications that require further design by the contractor, to prescriptive (closed) specifications where the design is already complete when the project is tendered.
Most projects involve a combination of performance and prescriptive specifications. Items crucial to the design may be specified prescriptively (such as external cladding) whilst less critical items, or items requiring specialist design may be specified only by performance (such as service lifts).
Performance specifications describe the result that is required from particular items and leave it to the contractor or supplier to satisfy that requirement. In effect it requires them to complete the design. The nature of the performance required is typically defined by the desired outcome, or by reference to standards. See Performance specification for more information.
Performance specified work is increasingly common as buildings become more complex and the supply chain becomes more integrated, with contractors and suppliers having greater involvement in design at an earlier stage of the project.
Performance specified work used to be most commonly defined in a ‘contractors designed portion’ as a supplement to the main contract, but increasingly now it forms part of the requirements of the main contract itself.
Separate sub-contractor design agreements are available where the main contractor is to design specific parts of the works and a sub-contractor is to design part or all of sub-contract works.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Listed despite problems with its design.
Zen and the art of cycling exploration.
Design Council Homes Taskforce launched
To support government 1.5 million homes target within UK climate commitments.
The story of this knowledge quarter building.
In ecology, in hydrology, in biology and in architecture.
Creating environments that promote physical, mental, and social well-being.
UK cases of neutral current diversion
Research project looks for example contributions.
Overstocking and macro-economics cause a decline.
The 2024 update of the Common Assessment Standard
Demonstrating organisational capability’ to fulfil roles under the Building Safety Act.
56 recommendations for a better built environment
Published by the CIC ahead of the King’s Speech.
SkillELECTRIC Top 8 Competitors Named
in annual search for the UK’s best student electrician.
CIOB Diversity and Inclusion technical information sheet
Step-by-step guide on implementing D and I practices.
Conservation and the Indian City. Book review.
Reversibility in conservation ethics
Learning from painting conservation.
Where It's AT Podcast launched!
New CIAT Architectural Technology Podcast goes live.